Pull-Out Test on pile

The Pull-Out Test is conducted to evaluate the uplift resistance of a pile under tensile loads. This test is crucial for structures subjected to forces that can pull the pile out of the ground, such as wind forces, tension in guy wires, or uplift in foundations due to water pressure or expansive soils.

Purpose

  1. Uplift Capacity:
    • Determine the maximum tensile load the pile can resist before failure.
  2. Pile-Skin Friction:
    • Assess the contribution of skin friction along the pile shaft in resisting uplift.
  3. Design Validation:
    • Verify design assumptions for piles subjected to tensile forces.
  4. Safety Assurance:
    • Ensure the pile meets the required uplift resistance for the intended application.

Applications

Test arrangement for pile pullout test Sketch on left is a schematic of the test setup
  1. Transmission Towers:
    • Piles supporting structures with guy wires experience significant uplift forces.
  2. Wind Turbine Foundations:
    • Require high resistance to uplift due to wind loads.
  3. Retaining Walls:
    • Anchor piles in tie-back systems resist tensile forces.
  4. Submarine Pipelines and Buoyant Structures:
    • Uplift forces due to buoyancy need to be counteracted by piles.

Principle

The pull-out test measures the tensile capacity of the pile by applying an upward load to the pile head. The load is incrementally increased until failure or the maximum test load is reached. The uplift resistance is primarily due to skin friction between the pile surface and the surrounding soil.

Testing Standards

  • IS 2911 (Part 4): Indian Standard for load testing of piles (Static and Dynamic load tests).
  • ASTM D3689: Standard Test Methods for Deep Foundations Under Static Axial Tensile Load.
  • BS EN 1997-1 (Eurocode 7): Geotechnical design – General rules for pile testing

Test Setup

Pull out test instrument
  1. Loading System:
    • Hydraulic jacks or similar equipment to apply upward loads.
  2. Reaction System:
    • Reaction piles, anchors, or heavy reaction beams provide resistance to the applied upward force.
  3. Measuring Devices:
    • Load Cells: Measure the applied tensile load.
    • Dial Gauges/Displacement Transducers: Measure the upward displacement of the pile.

Procedure

  1. Pile Preparation:
    • Expose the pile head and prepare it for load application.
    • Attach the hydraulic jack or loading system.
  2. Initial Readings:
    • Record the initial position and alignment of the pile.
  3. Load Application:
    • Apply tensile load in small increments (e.g., 20%, 40%, 60%, 80%, and 100% of the estimated ultimate load).
    • Hold each load increment for a specified time (e.g., 5-15 minutes) to observe deformation and load stabilization.
  4. Displacement Measurement:
    • Measure the upward displacement of the pile head at each load increment.
  5. Ultimate Load Determination:
    • Continue loading until:
      • The pile reaches failure (significant displacement without additional load increase).
      • Maximum test load as per the design is reached.
      • The safety limit of the reaction system is approached.
  6. Unloading:
    • Gradually release the load and record residual displacement to assess elastic recovery.

Data Analysis

  1. Load-Displacement Curve:
    • Plot the applied load against the measured displacement.
    • Identify the ultimate pull-out capacity where displacement increases significantly with no further increase in load.
  2. Uplift Capacity:
    • Determine the load at which the pile reaches failure or excessive displacement.
  3. Skin Friction Distribution:
    • Analyze the load transfer along the pile shaft to assess the contribution of skin friction.
  4. Elastic Recovery:
    • Measure the pile’s elastic deformation by comparing the initial and residual displacements.

Key Results

  1. Ultimate Uplift Capacity:
    • Maximum tensile load the pile can resist.
  2. Working Load:
    • Typically 50–60% of the ultimate load, considering a safety factor.
  3. Displacement Characteristics:
    • Uplift resistance is evaluated based on allowable displacement limits specified in the design.

Factors Influencing Results

  1. Soil Properties:
    • The type, density, and shear strength of the surrounding soil significantly affect uplift resistance.
  2. Pile Type:
    • Material and surface roughness impact skin friction.
  3. Pile Depth:
    • Longer piles generally provide higher uplift resistance due to increased skin friction.
  4. Groundwater:
    • The presence of water can reduce effective stress and skin friction, lowering uplift capacity.

Acceptance Criteria

  • Allowable Displacement:
    • Typically limited to 5-10 mm for working loads (varies by project specifications).
  • Safety Factor:
    • A safety factor of 2–3 is applied to determine the allowable uplift load from the ultimate capacity.

Advantages

  1. Direct Measurement:
    • Provides actual field data on tensile capacity.
  2. Comprehensive:
    • Assesses both ultimate and working capacities for design validation.
  3. Improves Design:
    • Helps refine pile length and material requirements.

Limitations

  1. Costly:
    • Requires specialized equipment and reaction systems.
  2. Time-Consuming:
    • Test setup and execution can take significant time.
  3. Limited Applicability:
    • Conducted on selected test piles, not all foundation piles.
  4. Soil Dependence:
    • Results are site-specific and may not generalize to other locations.

Comparison: Pull-Out Test vs. Other Tests

FeaturePull-Out TestStatic Load Test (Compression)Dynamic Load Test
Load DirectionUpward (tensile)Downward (compressive)Downward (via hammer impact)
PurposeEvaluate uplift capacityAssess axial compressive capacityEstimate capacity using stress waves
InstrumentationLoad cells, displacement gaugesLoad cells, settlement gaugesAccelerometers, strain gauges
CostModerate to HighHighLow to Moderate
Test DurationModerateLongShort

Conclusion

The Pull-Out Test is an essential tool for evaluating the uplift resistance of piles, especially for structures subjected to tensile forces. Providing direct field data ensures the safety and reliability of pile foundations under upward loads. Though more complex and costly than some other tests, its accuracy and relevance to real-world conditions make it a critical part of geotechnical investigations.

share now

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top